Acumen Fuse Metrics & Descriptions Guide

Metrics included in Acumen Fuse: 

Schedule Quality
Missing Logic
Logic Density™
Critical 
Hard Constraints
Negative Float
Insufficient Detail™ 
Number of Lags
Number of Leads
Merge Hotspots 
 
Advanced Metric Libraries
Characteristics
Total Activities
Milestones
Normal 
Summaries
Hammocks
Milestone Ratio 
Detail Level
Missing WBS
Longest Path
Riding Data Date
Activities per Million
Duration 
Original Duration
Remaining Duration 
Rem. Critical Duration
Rem. Non-Critical Duration 
Avg. Original Duration
Avg. Remaining Duration 
Ribbon Length
Schedule Overrun 
Logic   
Missing Predecessors
Missing Successors
Activities with Lags
SS Predecessors 
SF Predecessors
FF Predecessors
FS Predecessors
Logic Density™
Merge Hotspot 
Diverge Hotspot
Logic Hotspot™
Summary Links
Open Start
Open Finish 
Open Ends with Constraints
Open Ends w/out Constraints
Open Ends 
 Lags  
Lags
Hidden Duration
 Leads Maximum Lag  Minimum Lag 
Constraints
Constraint
As Late As Possible
Finish on or After
Finish on or Before
Must Finish On
Mandatory Finish
Must Start On
Mandatory Start
Start and Finish
Start On or After
Start and Finish
Start On or After
Start On or Before
Late Constraints
Early Constraints
Early Constraints
Free Float Constraints
Total Float Constraints
Soft Constraints
Hard Constraints
Unsatisfied Constraints
Float
Critical
Non-Critical
Negative Float 
Zero Days Float
0 to 20 Days Float
20 to 30 Days Float 
More than 30 Days Float
High Float
Average Float 
Max Float
Float Ratio 
Status
Underway
Planned
Completed 
Days Remaining
Days Completed
Completed Milestones 
Planned Milestones
Not Completed
Physical % Complete 
Duration % Complete
Units % Complete
Wrong Status 
Planned
Planned Ahead
Scheduled to Start 
Planned Delayed
Scheduled to Finish 
Planned on Schedule  
In-Progress      
Started Ahead
Started Delayed
In-Progress on Schedule 
Days Early
Days Late
Average Days Early 
Average Days Late
Average Start Variance
Discrepancy 
Actually Started
Expected Finish
Completed
Completed Ahead
Completed Delayed
Completed On-Schedule
Took Less than Planned
Accelerated
Days Variance
Days Early
Days Late
Average Days Early
Average Days Late
Average Variance
Actually Finished
Took Longer than Planned 
Baseline Compliance Analysis
Scheduled to Start
Scheduled to Finish
Started
Finished 
Started on Time
Started Early
Started Late
Finished on Time 
Finished Early
Finished Late
Started on Time/Finished Late
Start Variance
Start Compliance
Finish Variance
Finish Compliance 
Scenario Comparison
Critical
Soft Constraints
Hard Constraints 
Remaining Duration
Rem. Critical Duration
Ribbon Length
Avg. Float
Float Ratio
Longest Path 
 
Cost
Overrun
$ Cost Underrun
$ Cost Overrun 
$ Total Cost
$ Actual Cost
$ Remaining Cost 
$ Cost Discrepancy
$ Budget Cost
$ Cost per Day 
Negative Planned Cost
Negative Actual Cost
Risk Inputs
Aggressive
Conservative
Erroneous Risk Event
Broad Uncertainty Range
Scope Uncertainty
No Uncertainty
Average Uncertainty
Average Uncertainty Range
Wrong Uncertainty Range
No Downside
No Upside
 
Risk Exposure
High Criticality
Avg. Criticality
Schedule Risk Hot Spots™
Hidden Critical Paths
Avg. Duration Risk Contribution
Avg. Cost Risk Contribution
High Contingency
Earned Value
Cost Variance
Schedule Variance
SPI
CPI
Estimate at Complete
EAC (Using CPI Method)
EAC (CPI/SPI)
TCPI (Using BAC)
TCPI (Using EAC)
TCPI (EAC) to CPI 
Planned Value
Earned Value
Actual Cost
% Schedule
% Spent 
% Spent (EAC)
VAC
BAC
% Complete 
Earned Value Work
WV
SV
SPI
CPI
EAC 
EAC (CPI)
EAC (Composite)
TCPI (BAC)
TCPI (EAC)
TCPI (EAC) to CPI 
PV (BCWS)
EV (BCWS)
AC (ACWP)
% Schedule
% Spent 
% Complete
% Spent (EAC)
VAC
BAC 
Earned Schedule
 SV (t) SPI (t)    
Work/Resources
Overrun
Work Underrun
Work Overrun 
Total Work
Actual Work
Remaining Work 
Work Discrepancy
Baseline Work
Summarized Work 
Work per Day
Missing Resources
Resources 
Industry Standards
DCMA 14 Point Assessment
Logic
Leads
Lags
FS Relations 
Hard Constraint
High Float
Negative Float
High Duration
Invalid Dates
Resources
Missed Activities
Critical Path Test
CPLI
BEI 
GAO Best Practices
  1. Capturing all activities
  2. Sequencing all activities
  3. Assigning resources to all activities
  4. Establishing the duration of all activities
  5. Establishing the critical path for all activities
  6. Integrating schedule activities horizontally and vertically
  7. Establishing the critical path for all activities
  8. Identifying reasonable float between activities
  9. Conducting a schedule risk analysis
  10. Updating the schedule using logic and durations to determine the dates